InventivEnergy, an asset management firm, has selected NRG Energy Services, a wholly owned subsidiary of NRG Energy, to restart the Aspen Power biomass plant located in Lufkin, Texas.
NRG will also operate and maintain the facility once it resumes operation.
The plant first opened in August 2011 and was the first wood-fired biomass power plant in the state. It can consume about 525,000 tonnes of logging debris and municipal wood waste per year.
The Aspen power plant has the capacity to deliver approximately 50MW to the grid and uses locally sourced clean wood-waste biomass as its fuel supply.
Work to restart the facility began in mid-May and commercial operations are expected to be achieved by late July.
NRG is in the process of hiring the site management team and operating staff.
“The Aspen Power facility was shut down in the fall of 2012 due to market economics. Since then, our projections show an attractive opportunity for the plant to resume operations and provide competitivelypriced clean energy to the Texas market,” said John Keller, CEO and founder of InventivEnergy.